Mes-Año | Mar25 | Feb25 | Ene25 | Dic24 | Nov24 | Oct24 |
---|---|---|---|---|---|---|
Clasificación | C | C | A | D | A | A |
Clientes | 2320 | 2320 | 2365 | 2357 | 2283 | 2268 |
% Nivel Cobranza | 0.00% | 100.66% | 105.02% | 130.96% | 188.76% | 26.10% |
% Nivel Pérdida | 0.00% | -2.83% | -5.55% | 5.41% | -10.89% | -72.90% |
Energía Suministrada (GWh) | 0 | 3.2 | 4.14 | 4.84 | 4.06 | 5.05 |
Energía Facturada (GWh) | 0 | 3.29 | 4.37 | 4.58 | 4.5 | 8.74 |
Energía Cobrada (GWh) | 0 | 3.31 | 4.59 | 6 | 8.49 | 2.28 |
% Servicio | 99.72% | 100.00% | 98.60% | 100.00% | 99.93% | 99.99% |
% Sin Servicio | 0.28% | 0.00% | 1.40% | 0.00% | 0.07% | 0.01% |
Interrupción Programada (Hrs) | 0.00 | 0.00 | 8.00 | 0.00 | 0.00 | 0.00 |
Interrupción Ejecutada (Hrs) | 2.04 | 0.00 | 10.22 | 0.00 | 0.52 | 0.09 |
Promedio Interrupción Diarias (Hrs) | 0.07 | 0.00 | 0.34 | 0.00 | 0.02 | 0.00 |
Zona Universitaria (Parcial):C/ Robert Schombergk entre la Av. Independencia y George Washington, Av. Independencia desde la Robert Schombergk hasta la Máximo Gómez, Máximo Gómez desde la George Washington hasta casi la Benigno Filomeno De Rojas, Banco Agrícola, Embajada de España, Centro Cuesta Nacional (Máximo Gómez), Av. José Contreras desde la Av. Alma Mater hasta la Av. Máximo Gómez, Av. Santo Tomás de Aquino desde la Av. José Contreras hasta la Av. Independencia, Av. Independencia desde la C/ Santo Tomás de Auino hasta la Av. Máximo Gómez, Av. Bolivar desde la Av. Alma Mater hasta la Av. Máximo Gómez.