Circuito SANC102
Distribuidora EdeNorte - Provincia Samana
Mes-Año | Mar25 | Feb25 | Ene25 | Dic24 | Nov24 | Oct24 |
---|---|---|---|---|---|---|
Clasificación | B | B | B | B | B | B |
Clientes | 8 | 8 | 8 | 9 | 7 | 7 |
% Nivel Cobranza | 100.26% | 123.46% | 102.61% | 118.30% | 103.24% | 114.22% |
% Nivel Pérdida | 36.59% | 10.18% | 12.52% | 17.73% | 24.93% | 19.23% |
Energía Suministrada (GWh) | 0.11 | 0.11 | 0.13 | 0.14 | 0.13 | 0.12 |
Energía Facturada (GWh) | 0.07 | 0.1 | 0.11 | 0.11 | 0.1 | 0.1 |
Energía Cobrada (GWh) | 0.07 | 0.12 | 0.12 | 0.13 | 0.1 | 0.11 |
% Servicio | 99.41% | 99.46% | 98.51% | 96.55% | 98.64% | 99.62% |
% Sin Servicio | 0.59% | 0.54% | 1.49% | 3.45% | 1.36% | 0.38% |
Interrupción Programada (Hrs) | 10.00 | 0.00 | 8.00 | 8.00 | 0.00 | 4.00 |
Interrupción Ejecutada (Hrs) | 4.33 | 3.92 | 10.86 | 25.15 | 9.94 | 2.74 |
Promedio Interrupción Diarias (Hrs) | 0.14 | 0.13 | 0.36 | 0.83 | 0.33 | 0.09 |
Aeropuerto del Catey y Block & Hormigones Peninsular S. A.