Circuito RINC101FRO
Distribuidora EdeNorte - Provincia La Vega
Mes-Año | May25 | Abr25 | Mar25 | Feb25 | Ene25 | Dic24 |
---|---|---|---|---|---|---|
Clasificación | D | D | D | D | D | D |
Clientes | 358 | 358 | 355 | 352 | 325 | 328 |
% Nivel Cobranza | 0.00% | 80.78% | 94.60% | 73.81% | 80.99% | 91.59% |
% Nivel Pérdida | 0.00% | 64.82% | 68.46% | 57.02% | 61.40% | 72.16% |
Energía Suministrada (GWh) | 0 | 0.15 | 0.15 | 0.12 | 0.13 | 0.15 |
Energía Facturada (GWh) | 0 | 0.05 | 0.05 | 0.05 | 0.05 | 0.04 |
Energía Cobrada (GWh) | 0 | 0.04 | 0.04 | 0.04 | 0.04 | 0.04 |
% Servicio | 98.78% | 99.50% | 98.88% | 95.65% | 87.41% | 98.86% |
% Sin Servicio | 1.22% | 0.50% | 1.12% | 4.35% | 12.59% | 1.14% |
Interrupción Programada (Hrs) | 0.00 | 0.00 | 0.00 | 30.00 | 85.00 | 0.00 |
Interrupción Ejecutada (Hrs) | 8.88 | 3.63 | 8.21 | 31.78 | 91.88 | 8.29 |
Promedio Interrupción Diarias (Hrs) | 0.29 | 0.12 | 0.27 | 1.04 | 3.02 | 0.27 |
La Frontera y La Miseria.