Circuito PPRI101
Distribuidora EdeNorte - Provincia Santiago
| Mes-Año | Jun25 | May25 | Abr25 | Mar25 | Feb25 | Ene25 |
|---|---|---|---|---|---|---|
| Clasificación | A | A | A | A | A | A |
| Clientes | 1 | 1 | 1 | 1 | 1 | 1 |
| % Nivel Cobranza | 0.00% | 100.00% | 100.00% | 100.00% | 213.62% | 0.00% |
| % Nivel Pérdida | 0.00% | -4.03% | -13.51% | -7.37% | 2.82% | -13.48% |
| Energía Suministrada (GWh) | 0 | 0.46 | 0.48 | 0.54 | 0.58 | 0.56 |
| Energía Facturada (GWh) | 0 | 0.48 | 0.54 | 0.58 | 0.56 | 0.64 |
| Energía Cobrada (GWh) | 0 | 0.48 | 0.54 | 0.58 | 1.2 | 0 |
| % Servicio | 99.12% | 99.58% | 99.96% | 99.26% | 99.83% | 98.81% |
| % Sin Servicio | 0.88% | 0.42% | 0.04% | 0.74% | 0.17% | 1.19% |
| Interrupción Programada (Hrs) | 6.00 | 0.00 | 0.00 | 0.00 | 0.00 | 6.00 |
| Interrupción Ejecutada (Hrs) | 6.39 | 3.05 | 0.28 | 5.40 | 1.22 | 8.71 |
| Promedio Interrupción Diarias (Hrs) | 0.21 | 0.10 | 0.01 | 0.18 | 0.04 | 0.29 |