Circuito PIME101CUA
Distribuidora EdeNorte - Provincia Duarte
Mes-Año | May24 | Abr24 | Oct23 | Sep23 | Ago23 | Jul23 |
---|---|---|---|---|---|---|
Clasificación | C | C | C | C | C | C |
Clientes | 2408 | 2408 | 0 | 2407 | 2408 | 2417 |
% Nivel Cobranza | 0.00% | 0.00% | 90.55% | 67.92% | 98.39% | 85.62% |
% Nivel Pérdida | 0.00% | 0.00% | 60.54% | 59.69% | 60.65% | 60.86% |
Energía Suministrada (GWh) | 0 | 0 | 1.08 | 1.05 | 1.04 | 1.09 |
Energía Facturada (GWh) | 0 | 0 | 0.43 | 0.42 | 0.41 | 0.43 |
Energía Cobrada (GWh) | 0 | 0 | 0.39 | 0.29 | 0.4 | 0.37 |
% Servicio | 95.32% | 99.48% | 0.00% | 94.44% | 94.55% | 97.86% |
% Sin Servicio | 4.68% | 0.52% | 0.00% | 5.56% | 5.45% | 2.14% |
Interrupción Programada (Hrs) | 4.00 | 0.00 | 0.00 | 14.00 | 6.00 | 5.00 |
Interrupción Ejecutada (Hrs) | 34.20 | 3.78 | 0.00 | 40.59 | 39.81 | 15.62 |
Promedio Interrupción Diarias (Hrs) | 1.12 | 0.12 | 0.00 | 1.33 | 1.31 | 0.51 |
San Felipe, Patao, Pontón, Monte Negro, La Peña, Casa de Alto , Guanábano, Quebrada Los Patos, San Felipe Abajo, La Sabana, Buena Vista, Las Cabuyas El Calabazo, La Vereda, La Bajada, Chucho Vásquez, Pie de Plata, Coto, coto a medio, Ramonal, Ramonal Abajo, El Caimito, La Mesa, Chinguelo, Patao, Tawike, Palmarito, Los Botao, Dajamagual, Cienega Vieja, Lirios.