Circuito MOCA102SAR
Distribuidora EdeNorte - Provincia Espaillat
Mes-Año | May25 | Abr25 | Mar25 | Feb25 | Ene25 | Dic24 |
---|---|---|---|---|---|---|
Clasificación | C | C | C | C | C | C |
Clientes | 1267 | 1267 | 1256 | 1255 | 1246 | 1260 |
% Nivel Cobranza | 0.00% | 120.90% | 92.67% | 98.47% | 88.47% | 111.51% |
% Nivel Pérdida | 0.00% | 51.36% | 52.30% | 41.71% | 35.73% | 53.18% |
Energía Suministrada (GWh) | 0 | 0.53 | 0.58 | 0.47 | 0.5 | 0.55 |
Energía Facturada (GWh) | 0 | 0.26 | 0.28 | 0.27 | 0.32 | 0.26 |
Energía Cobrada (GWh) | 0 | 0.31 | 0.26 | 0.27 | 0.28 | 0.28 |
% Servicio | 98.53% | 99.40% | 98.04% | 96.87% | 92.12% | 99.04% |
% Sin Servicio | 1.47% | 0.60% | 1.96% | 3.13% | 7.88% | 0.96% |
Interrupción Programada (Hrs) | 0.00 | 0.00 | 5.00 | 18.00 | 52.00 | 6.00 |
Interrupción Ejecutada (Hrs) | 10.71 | 4.41 | 14.34 | 22.87 | 57.50 | 6.99 |
Promedio Interrupción Diarias (Hrs) | 0.35 | 0.14 | 0.47 | 0.75 | 1.89 | 0.23 |
Santa Rosa, Camino La Soledad, Carretera La Guazuma, Carretera Santa Rosa Parcial, Tierra Dura.