Circuito KQAZ101B
Distribuidora EdeSur - Provincia Azua
Mes-Año | Abr25 | Mar25 | Feb25 | Ene25 | Dic24 | Nov24 |
---|---|---|---|---|---|---|
Clasificación | D | D | D | B | A | B |
Clientes | 711 | 713 | 711 | 713 | 710 | 713 |
% Nivel Cobranza | 107.13% | 83.52% | 83.43% | 92.02% | 133.07% | 85.37% |
% Nivel Pérdida | 43.13% | -16.15% | 33.99% | 45.88% | 50.16% | -24.85% |
Energía Suministrada (GWh) | 0.63 | 0.36 | 0.53 | 0.58 | 0.6 | 0.25 |
Energía Facturada (GWh) | 0.36 | 0.41 | 0.35 | 0.31 | 0.3 | 0.32 |
Energía Cobrada (GWh) | 0.38 | 0.34 | 0.29 | 0.29 | 0.4 | 0.27 |
% Servicio | 99.07% | 99.23% | 100.00% | 99.47% | 99.98% | 99.81% |
% Sin Servicio | 0.93% | 0.77% | 0.00% | 0.53% | 0.02% | 0.19% |
Interrupción Programada (Hrs) | 2.00 | 0.00 | 3.00 | 1.00 | 0.00 | 0.00 |
Interrupción Ejecutada (Hrs) | 6.79 | 5.63 | 0.02 | 3.86 | 0.16 | 1.42 |
Promedio Interrupción Diarias (Hrs) | 0.22 | 0.19 | 0.00 | 0.13 | 0.01 | 0.05 |
Proyecto Ganadero, Pueblo Viejo, Barrera.