Circuito JUCO101B
Distribuidora EdeSur - Provincia Pedernales
Mes-Año | Abr25 | Mar25 | Feb25 | Ene25 | Dic24 | Nov24 |
---|---|---|---|---|---|---|
Clasificación | D | D | D | D | A | D |
Clientes | 2088 | 2116 | 2122 | 2119 | 2109 | 2132 |
% Nivel Cobranza | 77.15% | 85.03% | 76.53% | 76.75% | 75.03% | 77.08% |
% Nivel Pérdida | 73.61% | 72.62% | 66.77% | 69.66% | 72.81% | 65.32% |
Energía Suministrada (GWh) | 1.33 | 1.28 | 1.13 | 1.29 | 1.35 | 1.05 |
Energía Facturada (GWh) | 0.35 | 0.35 | 0.38 | 0.39 | 0.37 | 0.36 |
Energía Cobrada (GWh) | 0.27 | 0.3 | 0.29 | 0.3 | 0.28 | 0.28 |
% Servicio | 98.12% | 99.09% | 97.83% | 98.62% | 97.95% | 96.75% |
% Sin Servicio | 1.88% | 0.91% | 2.17% | 1.38% | 2.05% | 3.25% |
Interrupción Programada (Hrs) | 0.00 | 0.00 | 0.00 | 4.00 | 3.00 | 6.00 |
Interrupción Ejecutada (Hrs) | 13.71 | 6.66 | 15.82 | 10.07 | 14.96 | 23.74 |
Promedio Interrupción Diarias (Hrs) | 0.45 | 0.22 | 0.52 | 0.33 | 0.49 | 0.78 |
Ojeda, Los Patos, Los Blancos, Caletón, Las Merceditas, Paraíso, San Rafael.