Circuito GALL112-PONT
Distribuidora EdeNorte - Provincia Santiago
Mes-Año | Mar13 | Feb13 | Ene13 | Dic12 | Nov12 | Oct12 |
---|---|---|---|---|---|---|
Clasificación | D | D | D | D | D | D |
Clientes | 1243 | 1161 | 1139 | 1143 | 1167 | 1255 |
% Nivel Cobranza | 87.93% | 80.21% | 86.26% | 101.20% | 101.40% | 88.81% |
% Nivel Pérdida | 68.36% | 67.71% | 67.85% | 72.37% | 61.68% | 62.42% |
Energía Suministrada (GWh) | 0.64 | 0.61 | 0.62 | 0.63 | 0.54 | 0.57 |
Energía Facturada (GWh) | 0.2 | 0.2 | 0.2 | 0.18 | 0.21 | 0.22 |
Energía Cobrada (GWh) | 0.18 | 0.16 | 0.17 | 0.18 | 0.21 | 0.19 |
% Servicio | 60.35% | 68.56% | 68.78% | 79.74% | 67.01% | 63.16% |
% Sin Servicio | 39.65% | 31.44% | 31.22% | 20.26% | 32.99% | 36.84% |
Interrupción Programada (Hrs) | 330.00 | 294.00 | 322.00 | 247.00 | 308.00 | 341.00 |
Interrupción Ejecutada (Hrs) | 289.47 | 229.49 | 227.94 | 147.91 | 240.81 | 268.96 |
Promedio Interrupción Diarias (Hrs) | 9.52 | 7.54 | 7.49 | 4.86 | 7.92 | 8.84 |
Pontezuela, El Jobo, Urb. Las Orquídeas.