Circuito CHIV106HMA
Distribuidora EdeNorte - Provincia Duarte
Mes-Año | May25 | Abr25 | Mar25 | Feb25 | Oct19 | Sep19 |
---|---|---|---|---|---|---|
Clasificación | A | A | A | A | D | D |
Clientes | 0 | 0 | 0 | 0 | 0 | 3677 |
% Nivel Cobranza | 84.77% | 98.18% | 91.04% | 93.75% | 88.96% | 86.48% |
% Nivel Pérdida | 17.99% | 19.48% | 21.59% | 10.26% | -178.57% | 22.05% |
Energía Suministrada (GWh) | 0.96 | 0.85 | 0.9 | 0.73 | 0.2 | 0.6 |
Energía Facturada (GWh) | 0.79 | 0.68 | 0.7 | 0.65 | 0.55 | 0.47 |
Energía Cobrada (GWh) | 0.67 | 0.67 | 0.64 | 0.61 | 0.49 | 0.4 |
% Servicio | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 66.13% |
% Sin Servicio | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | 33.87% |
Interrupción Programada (Hrs) | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 326.00 |
Interrupción Ejecutada (Hrs) | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 247.26 |
Promedio Interrupción Diarias (Hrs) | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 8.13 |
Holguin Marte