Circuito CESP103JIC
Distribuidora EdeNorte - Provincia Dajabon
Mes-Año | Mar25 | Feb25 | Ene25 | Dic24 | Nov24 | Oct24 |
---|---|---|---|---|---|---|
Clasificación | C | C | C | C | C | C |
Clientes | 1251 | 1251 | 1232 | 1230 | 1262 | 1260 |
% Nivel Cobranza | 0.00% | 91.27% | 95.50% | 110.58% | 96.72% | 99.20% |
% Nivel Pérdida | 0.00% | 49.25% | 45.50% | 54.94% | 46.33% | 53.04% |
Energía Suministrada (GWh) | 0 | 0.42 | 0.38 | 0.43 | 0.42 | 0.53 |
Energía Facturada (GWh) | 0 | 0.21 | 0.21 | 0.19 | 0.23 | 0.25 |
Energía Cobrada (GWh) | 0 | 0.19 | 0.2 | 0.22 | 0.22 | 0.25 |
% Servicio | 97.88% | 97.13% | 92.25% | 97.14% | 99.15% | 97.86% |
% Sin Servicio | 2.12% | 2.87% | 7.75% | 2.86% | 0.85% | 2.14% |
Interrupción Programada (Hrs) | 5.00 | 18.00 | 55.00 | 4.00 | 10.00 | 0.00 |
Interrupción Ejecutada (Hrs) | 15.45 | 20.94 | 56.56 | 20.87 | 6.19 | 15.63 |
Promedio Interrupción Diarias (Hrs) | 0.51 | 0.69 | 1.86 | 0.69 | 0.20 | 0.51 |
Damajagua, el Palo.