Circuito ABAP101MAV
Distribuidora EdeNorte - Provincia Duarte
Mes-Año | Mar25 | Feb25 | Ene25 | Dic24 | Nov24 | Oct24 |
---|---|---|---|---|---|---|
Clasificación | D | D | D | D | D | D |
Clientes | 589 | 589 | 529 | 540 | 593 | 600 |
% Nivel Cobranza | 0.00% | 67.73% | 66.24% | 72.76% | 90.31% | 94.19% |
% Nivel Pérdida | 0.00% | 60.94% | 67.07% | 72.15% | 68.10% | 67.18% |
Energía Suministrada (GWh) | 0 | 0.34 | 0.36 | 0.36 | 0.36 | 0.37 |
Energía Facturada (GWh) | 0 | 0.13 | 0.12 | 0.1 | 0.11 | 0.12 |
Energía Cobrada (GWh) | 0 | 0.09 | 0.08 | 0.07 | 0.1 | 0.11 |
% Servicio | 97.21% | 95.03% | 88.17% | 99.61% | 97.71% | 97.51% |
% Sin Servicio | 2.79% | 4.97% | 11.83% | 0.39% | 2.29% | 2.49% |
Interrupción Programada (Hrs) | 0.00 | 30.00 | 84.00 | 0.00 | 8.00 | 0.00 |
Interrupción Ejecutada (Hrs) | 20.35 | 36.25 | 86.35 | 2.88 | 16.69 | 18.18 |
Promedio Interrupción Diarias (Hrs) | 0.67 | 1.19 | 2.84 | 0.09 | 0.55 | 0.60 |
Madre Vieja, El Indio, Loma La Candela, Joboban, Ceiba Gorda, La Punta.